18 people standing in front of firetruck holding shovel with dirt, ground breaking event

Joint Station: Fire 5-2 Paramedic Response

The Town of Stouffville and The Regional Municipality of York have officially broke ground on a new joint Fire and Paramedic Response Station at 4902 Aurora Road in Ballantrae. The new Fire Station 5-2 and Paramedic Services Station 20 represents a collaborative investment between the Town and York Region to enhance emergency response services in Stouffville’s growing northern area. 

Features of the New Facility

Size & Structure: The building will be about 18,500 sq ft with three fire bays and two ambulance bays to support 24/7 operations for both fire and paramedic crews. 

Optimized Layout: The station will be purpose-built to enable quicker dispatch, improve emergency response times, and serve as a contemporary hub for training, operations, and community readiness. 

Modern, Sustainable Design: The station is being designed to achieve LEED Silver certification for energy efficiency and sustainability. 

State-of-the-Art Spaces: It will include modern crew facilities, space for equipment, improved response dispatch capabilities, and room for training and operations planning.

Elevated front view rendering of new facility and surrounding grounds, 5 garage doors

Project Benefits

Improved Emergency Response: The new location and facility are intended to improve emergency response times and provide more efficient service for both fire and paramedic teams. 

Stronger Health & Safety Network: By co-locating fire and paramedic services, collaboration and resource sharing are improved, helping maintain high-quality patient care and public safety coverage across the region.

Community Safety & Growth: It supports the town’s growth and community safety needs with modern infrastructure built for long-term use.

Current Phase / Status

Construction Phase

Construction of the new Joint Fire and Paramedic Station has entered the main building phase. Most of the underground site servicing work has been completed, with the remaining service connections being finalized alongside building construction.

Work is now focused on building the structure itself, including the steel framework, floor and roof decking, exterior masonry walls, underground building services, and the building's exterior enclosure.

This marks an important milestone for the project, as the station is now becoming visible above ground and several construction trades are working on site at the same time. Over the coming months, crews will continue advancing the building through coordinated structural, mechanical, electrical, masonry, and exterior building work.

Construction activity remains ongoing throughout the site, with the project team coordinating work to maintain progress and keep the project moving efficiently into the next stage.

York Region and the Town of Stouffville are building safer, stronger and more resilient communities for today and for generations to come. Construction will be led by Pegah Construction Limited, with architectural design by Thomas Brown Architects Inc.

The total project cost is approximately $14.5 million, with funding shared between the Town and the Region. Substantial completion is expected in fall 2027. 

 

Progress Update:
  • Structural steel installation is nearing completion, with the main building frame expected to be substantially complete by the beginning of Fall 2026.
  • Installation of the metal roof and floor decking is scheduled to begin within the coming week and continue into early Fall 2026.
  • Construction of the exterior masonry walls is underway and will continue through early Fall 2026 as the building envelope takes shape.
  • Waterproofing work is underway on exterior foundation and masonry wall areas to help protect the building from moisture.
  • Construction of the parapets (the portions of wall extending above the roofline) is scheduled to begin in early Fall 2026.
  • Remaining site servicing and underground infrastructure work will continue and be coordinated with ongoing building construction activities.

What Residents will Notice

Residents can expect to see the building's structure and exterior walls continue to grow over the coming weeks. Activity on site will remain visible as multiple construction teams work concurrently to advance the project toward the next phase of construction.

Contact:
Timeline:

Initiation 

Joint Station: Fire 5-2 & Paramedic Response has finished this stage 

  • Identify the need for a new Fire Hall and Paramedic Station to support emergency response in the community
  • Confirm the project location, overall goals, and secure initial approvals 

Planning 

Joint Station: Fire 5-2 & Paramedic Response has finished this stage 

  • Create a project plan that outlines timing, budget, and key milestones 
  • Complete studies and approvals needed to prepare a vacant site for development 

Design

Joint Station: Fire 5-2 & Paramedic Response has finished this stage 

  • Design a modern facility that supports emergency response, staff safety, and future community needs
  • Incorporate sustainable and energy-efficient features into the building design 

Site Servicing & Preparation

Joint Station: Fire 5-2 & Paramedic Response is currently at this stage 

  • Bring services such as water, sewer, power, and access roads to the site
  • Prepare the land through grading and site work to get it ready for construction 

Construction

  • Build the Fire Hall and Paramedic Station structure and vehicle bays  
  • Continue to monitor safety, quality, and progress throughout construction 

Interior Fit-Out

  • Complete interior spaces including vehicle bays, living areas, training rooms, and workspaces
  • Install equipment, technology, and building systems needed for daily operations 

Completion: Fall 2027

  • Finish final inspections and prepare the building for occupancy
  • Open the new Fire Hall and Paramedic Station for service to the community 

Accessible formats available upon request. Contact 905-640-1900 or customer.service@townofws.ca for assistance.
© 2024 Town of Whitchurch-Stouffville  | Privacy and Disclaimer

Scroll to top